Road Closure – High Street, Walkern

‘Please ensure you have moved your car on the date below’

Resurfacing worksin High Street, Walkern

Works will be carried outfrom the junction of White Hill up to and including the junction area at Finches End

On Thursday 3 August 2023toThursday 10 August 2023

Works between 9:30amand4:00pm

There will be no works carried out over the weekend

We are writing to tell you about works we’ll be undertaking in your area.

What you need to do:

  • If you need to use your vehicle, please make sure you move it outside the road closure area shown on this letter, at least 30 minutes before we are due to start working.

What you need to know:

  • Vehicles may not be allowed access through the road closure during the works, except for emergency vehicles. We are unable to provide information of which part of the road will have access and when. Please speak to the on-site team on the day who will be able to advise on access.
  • Please refer to the yellow signboards on your street to see the exact dates, timings and permit number. Any date changes to these works will be communicated on the yellow signboards at either end of your street and at hertfordshire.gov.uk/roadclosures
  • These works are weather dependent and may be postponed if poor weather is forecast.
  • Details of any disruptions to bus services can be found at intalink.org.uk/timetables(search for your service). If you’re unable to find this information please call our customer service centre on 0300 123 4050.
  • All local businesses will be open as usual.

These works will be completed as per the phasing plan below

SUMMARY OF WORKS

Work dates/times/Phasing

Phase 1

High Street

Start @ 30mph sign to before Dovehouse Lane

3rd/4thAugust 2023

Works Description

Image3

Traffic Management

Road closure during the working hours.

9.30am to 4.00pm

Phase 2

Work dates/times/Phasing

High Street

Before Dovehouse Lane to between Totts Lane & Froghall Lane

7th/8th August 2023

Work dates/times/Phasing

Image4

Traffic Management

Road closure during the working hours.

9.30am to 4.00pm

Work dates/times/Phasing

Phase 3

High Street

Between Totts Lane& Froghall to end at No.6 and down to Finches

9th/10thAugust 2023

Works Description

Image5

Traffic Management

Road closure during the working hours.

9.30am to 4.00pm

Note.

  • Location of the surfacing works may alter subject to site conditions or unforeseen circumstances.

Further information:

We understand these works may be an inconvenience to you, however, we ask you to support us as we make the necessary improvements.

For live traffic information and news across Hertfordshire, please follow us on social media and subscribe to our UpdateMe bulletins.

Diversion Route:

Image9

Image5

 

CWY230364-1 High Street Walkern 636L